Guide · Ordering

After the Deposit — What You Hear and Receive, Stage by Stage

This page belongs to the page about how an order runs at the factory, which makes hookah coals, also called shisha charcoal. It covers the weeks a buyer cannot see: from the first payment to the moment the balance falls due.

Written by
Rudi Kurniawan
Published
Updated
Charcoal shipped by sea as UN 1361 rests between production and packing; the rest period is called weathering.

Quick answer

I have paid the deposit: what happens now, and what will I see before the balance is due?

After the first payment an order of hookah coals passes through production, the rest period, packing, loading and the documents. Each stage has a named desk and something a buyer can ask to see. The factory states 30 to 40 days from the first payment to loading for a first order. No schedule of updates is promised, so ask for what you want to see before each stage begins.

1. Stage by stage: desk, what happens, what you can ask to see

After the first payment an order passes through seven stages. Each has a desk that answers for it and something you can ask to see.

Definition

down payment

A down payment is the first part of an order's price, paid before production starts; the remainder is the balance.

The seven stages of an order of hookah coals after the first payment: the desk that answers for each stage, what happens, and what a buyer can ask to see. Desk leads as declared by the factory.
StageDeskWhat happensWhat you can ask to see
1. Production is scheduled Production: Doni SetiawanThe order takes its place in the production plan; the coals are made to orderThe planned loading date, in writing
2. Pressing and drying Production: Doni SetiawanThe coals are pressed in your shape and dried in the ovensPhotos of the pressed coals on trays
3. Rest period Production: Doni SetiawanThe dried coals rest before they may be packedThe production date of your batch
4. Packing Warehouse and packing: Nurul Tri BudiThe coals go into inner units and master cartons; printed boxes follow the approved proofA printed box beside its proof; the marks on a carton
5. Loading Shipping and documents: Dwi SaputroThe cartons are counted and loaded, and the container is sealedLoading photos; the container and seal numbers
6. Documents Shipping and documents: Dwi SaputroThe papers of the shipment are preparedThe drafts, the draft bill of lading among them
7. Balance Accounts: Ratna LestariThe balance falls due as your proforma invoice statesThe line of the invoice that names what the balance is paid against

For the stages up to loading the factory states 30 to 40 days for a first order and 25 to 35 days for a repeat order, counted from the first payment to loading. What that time is made of is on the page about capacity and lead time.

Note

The factory has declared no reply time and no schedule of updates, so this page promises neither. What it lists is what exists at each stage and can be shown on request.

2. The quiet stage: the rest period

One stage looks like a delay and is not one. After drying, the coals rest before they may be packed, and nothing visible happens to the order.

Special provision 978 sets three figures for UN 1361 charcoal: at least 14 days of weathering after production before packing, a material temperature of no more than 40 °C on the day of packing, and at least 30 cm of headspace in the container. Carriers ask for a dangerous goods declaration, a weathering certificate and a stuffing (vanning) certificate. (The provision allows an inert-gas packing route and approval by the competent authority as alternatives to 14 days of weathering. Rules on stacking height and gaps between packages were seen in one secondary source only and are not stated on the site.)

Source: Resolution MSC.556(108): Amendments to the IMDG Code, special provision 978 (opens in new tab), International Maritime Organization, accessed

Pressing gives a charcoal briquette its shape and size, and the size sets how many pieces weigh one kilogram.

The rest period is a rule for every supplier of charcoal by sea, so no factory can skip it for an urgent order. What the provision asks, and how the dates are recorded, is on the page about the loading conditions for charcoal.

Tip

Ask for the production date of your batch when drying ends. From that date you can count the rest period yourself.

3. What to ask for, and when

Ask before the stage, not after it. A photo of coals on the trays can be taken on the day they are pressed and not a week later.

  • With the first payment: ask for the planned loading date and say which stages you want to see.
  • Before pressing: ask for photos of the pressed coals with a ruler or a caliper in frame.
  • Before packing: for your own brand, ask for a printed box beside the proof you approved. The proof step is on the page about private label steps and minimums.
  • Before loading: ask for loading photos and for the container and seal numbers.
  • Before the vessel sails: ask for the drafts of the papers.
The carton count on the packing list has to match the cartons loaded into the container.

Send each request to the desk named in the table, through the contact form, with your order reference. A request that names the stage and the photo is one the desk can act on.

Caution

A change to the specification or to the artwork after the first payment is a new signed sheet, and it can move the loading date. Ask what it does to the date before you confirm it.

4. Before the balance falls due

The balance is the last point at which you can check before the container is yours to collect. The factory states its payment stages as a 50% down payment and the balance against documents.

  • The loading photos show your cartons, your marks and the space under the roof.
  • The container and seal numbers on the photos match the drafts.
  • The drafts carry your company name, the product description and the weights as you gave them.
  • The bank account is the one on your proforma invoice, in the company's legal name.

Which papers the factory issues, and which come from the carrier or a surveyor, is on the page of export documents. How the container is released after the balance is on the page about the bill of lading and release, and the stages themselves on the page about payment terms.

Important

If a message asks you to pay the balance to a different account, stop. Confirm through the contact form before any transfer.

Questions and answers

What happens after I pay the down payment?
Production is scheduled, then the coals are pressed, dried, rested, packed and loaded, and the papers are prepared. The factory states 30 to 40 days from the first payment to loading for a first order.
Will the factory send production updates?
No update schedule is declared, so this page promises none. Ask for what you want to see, such as photos of the pressed coals, the printed box against its proof or the loading, before that stage begins.
Why is there a pause between drying and packing?
Charcoal must be weathered for at least 14 days after production before it is packed, under special provision 978 of the IMDG Code. Nothing visible happens to the order in that period.

Sources