Quick answer
How many containers a month can this factory make for me, and how long does an order take?
The plant makes a declared 7 tons a day. Multiplied by the days it runs each month and divided by the load of your container, that gives the containers a month it can fill. Lead time has a floor: charcoal must rest at least 14 days after production before it is packed.
Capacity and lead time at a glance
As declared, November 2026
- Daily output
- 7 tons per day
- Drying ovens
- 6, fired with wood pellets
- Container sizes
- 20 ft and 40 ft
- 20 ft load, 25 mm cubes
- 20 t (planning figure)
- 40 ft load
- 26.5 t (planning figure)
- Lead time
- Stated in your quote
1. From daily output to containers a month
The declared output is 7 tons per day. A monthly figure follows from two more numbers: the days the plant runs and the load of one container.
| Step | Arithmetic | Result |
|---|---|---|
| Output in the example month | 7 t × 25 days | 175 t |
| 20 ft containers, 25 mm cubes | 175 t ÷ 20 t | about 8 |
| 40 ft containers | 175 t ÷ 26.5 t | about 6 |
Caution
This is an example. The factory has not stated how many days a month the plant runs, and the loads are planning figures. Your quote states both for your order.
Why a 20 ft load changes with the shape, and a 40 ft load does not, is on the page about container loads.
2. What sets lead time
Lead time is the sum of six steps, and only some of them depend on the factory.
Definition
lead time
Lead time is the time from a confirmed order to the day the loaded container leaves the factory.
-
Queue
Orders ahead of yours. A new order waits for the orders already planned on the presses.
-
Pressing and drying
Set by daily output. The volume of your order divided by the daily output gives the pressing days; drying follows each pressing day.
-
Weathering
A fixed minimum. The dried coals rest before they may be packed. This step has a floor set by a rule, not by the factory.
-
Packing
Depends on the boxes. Printed boxes have to arrive before packing can start; neutral cartons do not wait for printing.
-
Loading
One container at a time. Cartons are counted, loaded and photographed, and the container is sealed.
-
Booking
The carrier sets the sailing. The container is booked as dangerous goods, and the sailing date depends on the carrier.
The floor under the third step is a rule: Special provision 978 sets three figures for UN 1361 charcoal: at least 14 days of weathering after production before packing, a material temperature of no more than 40 °C on the day of packing, and at least 30 cm of headspace in the container. Carriers ask for a dangerous goods declaration, a weathering certificate and a stuffing (vanning) certificate. (The provision allows an inert-gas packing route and approval by the competent authority as alternatives to 14 days of weathering. Rules on stacking height and gaps between packages were seen in one secondary source only and are not stated on the site.)
What that rule asks of every container is on the page about loading conditions for charcoal.
3. What shortens lead time
A buyer cannot shorten weathering, but three things on the buyer's side decide whether an order starts on time.
- Artwork ready. Printing waits for your approval of the proof.
- Specification signed. Both sides sign the specification before production.
- First payment on time. In the order steps, the proforma invoice and the first payment come before production.
Where each of these sits in an order is on the page of the seven order steps.
Note
This page states no stock position and promises no date. The date for your order is in your quote.
4. Reserve a production slot
To reserve a slot, send the quote sheet with a target loading date. Production checks the date against the orders already planned and the rest period, and the quote states the lead time.
The sheet is the factory quote sheet; the target date is its last field.
Tip
Give the date you need the container loaded, not the date you need it to arrive. The sailing time is the carrier's, and it is not part of the factory's lead time.
Questions and answers
How long does it take to produce a container of hookah coals?
How many containers a month can the factory fill?
Sources
- Resolution MSC.556(108): Amendments to the IMDG Code, special provision 978 (opens in new tab), International Maritime Organization — accessed